Gravel shed base, step by step

A timber frame, weed membrane, 100 mm of compacted sub-base and 50 mm of gravel on top. For an 8 x 6 ft shed it is two days for one person.

Eight steps in four stages

  1. Steps 1 and 2: mark out and dig

    Peg out 150 mm wider than the shed all round; check the diagonals match. Dig out 150 mm, roots and all.

    Two empty wheelbarrows on a block-paved yard
  2. Steps 3 and 4: build and level the frame

    Screw four 150 x 47 mm treated boards into a box, stake it every metre and level it both ways.

    A saw, a square and a tape measure lying on timber planks
  3. Steps 5 and 6: membrane and sub-base

    Lay membrane with 150 mm overlaps. Spread MOT Type 1 in two 50 mm layers, compacting each.

    Heaps of grey crushed stone beside a path
  4. Steps 7 and 8: gravel and bearers

    Fill to the frame's edge with 20 mm angular gravel. Lay treated bearers, check the level, set the shed.

    Treated timber bearers laid across a plastic grid base filled with grey gravel

Materials list for an 8 x 6 ft shed

For a base of 2.6 x 2.0 m. Picks marked as examples show the kind of product to look for.

  • Treated timber, 150 x 47 mm2 lengths of 4.8 m
  • Timber stakes, 50 x 50 x 600 mm8
  • Exterior screws, 75 mm1 box of 100
  • Weed membrane, 100 g/m², example pick1 roll, 2 x 10 m
  • MOT Type 1 sub-base1 bulk bag
  • Angular gravel, 20 mm1 bulk bag
  • Treated bearers, 75 x 50 mm, example pick5 lengths of 2.4 m
  • Plate compactor, or a hand tamper1 day's hire
An old wooden spirit level with a brass vial on a sackcloth surface

Gravel base costs

A worked example for the 2.6 x 2.0 m base above, about £310 in all.

ItemQuantityExample price
Treated timber, 150 x 47 mm2 x 4.8 m£36
Timber stakesPack of 8£14
Exterior screws, 75 mmBox of 100£8
Weed membrane2 x 10 m£15
MOT Type 1 sub-baseBulk bag£75
Angular gravel, 20 mmBulk bag£80
Treated bearers, 75 x 50 mm5 x 2.4 m£35
Plate compactor hire1 day£45
Total£308

Example prices from builders' merchants in autumn 2026. Delivery of bulk bags is often extra; a hand tamper saves the hire.

Sawn timber boards stacked in a yard

Gravel base questions

How deep should a gravel shed base be?

About 150 mm: 100 mm of compacted sub-base and 50 mm of gravel. On clay or soft ground, dig another 50 mm.

Can a shed sit straight on gravel?

Not on the stones alone. Set the floor on treated bearers or a plastic grid, so air moves under it.

Which gravel suits a shed base?

Angular, 10 to 20 mm. The edges lock under weight; round pea shingle rolls and lets bearers sink.

Gravel or a concrete shed base?

For a timber shed up to about 10 x 8 ft, usually: it costs less and drains. Pour concrete for a heavy workshop or a log cabin.