Why gravel works
A shed rots from the bottom up. Water that sits under the floor is what kills joists, so the job of a base is to stay level and let water drain away. A bed of clean crushed stone does both. Rain runs straight through it, the stones lock together when compacted, and the timber frame stops the edges spreading.
It's also forgiving. If the ground settles a little over the years, you can rake in more stone and re-level. Try that with a slab.
Check first: some towns need a permit for sheds over a certain size, or set a minimum distance from your boundary. Call 811 (or your local utility-locating service) a few days before you dig.
Materials list
For an 8 × 10 ft shed, build a pad 10 × 12 ft: a foot of extra gravel on every side keeps drips off the walls and gives you somewhere to stand a ladder.
- Pressure-treated 4×6 timbers, 12 ft, rated for ground contact4
- Clean ¾ in crushed stone (no fines)about 2.2 tons
- Woven landscape fabric120 sq ft
- ½ in rebar, cut to 24 in8 pieces
- 10 in structural timber screws12
- Plate compactor, hired for a day1
Tools: tape measure, string line and stakes, 4 ft level, spade, rake, wheelbarrow, circular saw, drill with a long ½ in bit, and a sledgehammer for the rebar.
A 3.2 oz woven polypropylene landscape fabric
Woven fabric lets water through but stops stone sinking into the soil. Skip the thin non-woven rolls sold for flower beds.
Check the priceThe steps
-
Mark out the pad
Drive a stake at each corner of a 10 × 12 ft rectangle and run string between them. Measure both diagonals: when they match, the corners are square.
-
Strip the turf and level the soil
Dig out grass and roots across the whole pad, about 4 in down. Find the high corner and work from it. On a gentle slope, dig into the high side rather than building up the low side.
-
Build and set the frame
Cut two timbers to 10 ft and screw the corners together with two timber screws per joint, staggered. Set the frame in the trench, then check it is level across both directions and along each side. Pack or dig under the timbers until the bubble sits in the middle.
-
Pin the frame down
Drill a ½ in hole through the timber 12 in from each corner, then drive a 24 in length of rebar through it into the ground until it sits flush. Eight pins stop the frame creeping as the stone settles.
-
Lay landscape fabric
Line the inside of the frame, overlapping joins by 12 in and running the edges a few inches up the timber. It keeps weeds out and stops stone disappearing into soft ground.
-
Fill and compact in two layers
Spread 2 in of stone, wet it lightly and run the plate compactor over it twice. Repeat with the second layer until the stone sits level with the top of the frame.
-
Check level and screed
Drag a straight 2×4 across the frame to strike off high spots, fill the low ones, and give it a last pass with the compactor. Your shed's floor bearers can go straight on top.
What it costs
Here's a worked example for the 10 × 12 ft pad above. Prices are our sample estimates for late 2026, not quotes: stone and delivery in particular vary a lot by area.
| Item | Cost | Share of total |
|---|---|---|
| Crushed stone, 2.2 tons, delivered | $175 | |
| Treated 4×6 timbers (4) | $96 | |
| Plate compactor hire, 1 day | $85 | |
| Timber screws (12) | $30 | |
| Rebar, 8 pins | $24 | |
| Landscape fabric | $22 | |
| Total | $432 |
How does that compare with other bases? The ranges below are our rough DIY estimates for the same 8 × 10 ft shed, materials and tool hire only. Gravel isn't the cheapest option on paper, but it's the one that is hardest to get wrong.
Shed base cost, 8 × 10 ft shed
Sample estimate ranges in US dollars, DIY. Not quotes.
Ground-contact rated 4×6 treated timber
Look for a "ground contact" or UC4 rating on the end tag. Lumber treated only for above-ground use will soften within a few years when it sits in damp stone.
Check the priceQuestions people ask
How deep should the gravel be?
Four inches of compacted stone suits most garden sheds up to about 10 × 12 ft. On clay or soft ground, dig deeper and go to 6 in.
Can I use pea gravel?
Not for the base. Pea gravel is round and rolls under load, so it never locks together. Use angular crushed stone with the fines washed out.
Do I need a plate compactor?
For a pad this size, yes. A hand tamper will do a small 6 × 4 ft base, but on 120 sq ft it's slow, tiring and less even. A day's hire is usually worth it.
Can the shed sit straight on the gravel?
Most kit sheds come with floor bearers (runners) that sit directly on the stone. If yours doesn't, lay treated 4×4s across the pad every 16 to 24 in.